Oak Gardens Update _ 31st October 2024

Our team has been diligently working this week, despite challenging weather conditions, to complete the foundations up to the damp proof course (DPC) for Plot Number 6. Tomorrow, Cattons Recycling will be onsite to pour the cement for the slabs, marking a significant milestone in the project’s progression.

In other areas of the site, Finnies Plumbing & Heating has successfully installed the underfloor heating systems in Plots 7 and 8. This advancement contributes to our commitment to ensuring a comfortable and energy-efficient environment in Cobnut Homes properties.

Check in next week for more exciting news!