Significant progress has been achieved at the Oak Gardens site over the past week. The groundwork for Plot 6 has been successfully completed, with the area fully pegged out in preparation for the scheduled cement pour next week.
Today, we received the delivery of a drying room container, ensuring our site team is well-prepared for the upcoming winter months. This facility will provide a comfortable space for staff to dry and store equipment during colder weather, supporting continued productivity on-site.