Oak Gardens Newsletter _ 26th April 2024

Our joiners @ CP Joinery have been busy this week constructing the ground floor ceilings in Plot 7 and are prepared ready  for the  plasterboard installation 4 x 1

In Plot 8  our teams have been busy, and the tile installation is underway for over the garage, and initial work has commenced on the small roofs over the chimney

Plumbing and ground floor insulation has been initiated, with preparations underway for dormers.

Check in next week for more exciting news.