Our joiners @ CP Joinery have been busy this week constructing the ground floor ceilings in Plot 7 and are prepared ready for the plasterboard installation 4 x 1
In Plot 8 our teams have been busy, and the tile installation is underway for over the garage, and initial work has commenced on the small roofs over the chimney
Plumbing and ground floor insulation has been initiated, with preparations underway for dormers.
Check in next week for more exciting news.