This week, TP Construction has been focusing on the installation and alignment of road kerbs, marking an important stage in the ongoing construction works. This process establishes the boundaries and layout of the road, ensuring the correct levels, alignment and drainage provisions are in place ahead of the next phase.
With the kerbing works progressing, the team is preparing for the application of the surface course. This final layer will not only provide a durable, high-quality driving surface but will also play a key role in defining the overall aesthetic appearance and finish of the road and driveway.
These works represent another significant step towards completing the external infrastructure, bringing the project closer to its finished appearance.
Elsewhere on site, the air source heat pumps supplied by Stiebel Eltron have now been installed and are ready for commissioning and start-up. This marks an important milestone in the progress of the building services installation, bringing the project one step closer to having its heating systems fully operational.
Once commissioned, the systems will provide an efficient and sustainable heating solution, supporting the building’s long-term energy performance and overall environmental credentials.